in Eppelheim
Deutsche SiSi-Werke BA II

Eppelheim

9,625 sqm

150 / 100 / 16 m

Production facilities, Logistics building

extended shell

Sep. 2013 – June 2014

Construction stage 2 consists of 4 individual buildings – buildings HPW 4–7 – comprising a 3 storey logistics building with upper-level office and social facility section, a 3-storey technical and service building, a high-bay warehouse and a transport bridge. Special foundations are needed for the 1 m thick base of the 5,500 m² high-bay warehouse. The entire structure consists of precast reinforced concrete elements from BREMER's own production plants. Because of food industry regulations, work in all trades needs to be carried out to higher standards. The architecture is in line with the company's CI, which is maintained worldwide.
After the on-time completion of construction stage 1 to the client's satisfaction, Wild awards us the second construction stage directly afterwards.