BEOS production facility and office in Glinde GlinnkampBEOS production facility and office in Glinde Glinnkamp1BEOS production facility and office in Glinde Glinnkamp2BEOS production facility and office in Glinde Glinnkamp3BEOS production facility and office in Glinde Glinnkamp4BEOS production facility and office in Glinde Glinnkamp5
 
Building data
Location
Glinde Glinnkamp
Floor area
5,422 sqm
Length/width/height
65 / 58 / 14.00 m
Type of building
Production facilities,  Office buildings
Scope of supply and services
turnkey
Period of construction
Oct 2018 - Aug. 2019
Description of the facility

The development consists of 3 building sections catering for office, digitisation and warehouse operations.

BS 1 is the hall area. Document consignments are loaded/unloaded at 2 receiving gates with dock levellers.

BS 2 is the digitisation zone.

BS 3 is the 3-storey office and social section. The ground floor accommodates offices, changing rooms and social facilities and the two upper storeys provide office space for Reisswolf administration and management.