Goodman WMF extension

in Dornstadt

Goodman WMF extension in Dornstadt5Goodman WMF extension in Dornstadt6Goodman WMF extension in Dornstadt7Goodman WMF extension in Dornstadt8Goodman WMF extension in Dornstadt9
 
Building data
Location
Dornstadt
Floor area
20,765 sqm
Length/width/height
151 / 121 / 14 m
Type of building
Logistics building
Scope of supply and services
turnkey
Period of construction
Jan. 2015 – Oct. 2015
Special features
Extension of the logistics building erected in 2011 with extensive earthworks.

Description of the facility
One axis of the existing building is upgraded to a fire wall. To raise the building to the required level, approx. 65,000 m³ of earth needs to be moved. The building is fronted by a two-storey office. The hall structure consists of precast reinforced concrete elements and features a change of roof level. An automated small parts store with a depth of 12 m and a floor area of 4,500 m³ is also realised on a mezzanine level.