Zajadacz production facility

in Neu-Wulmstorf

 
Building data
Location
Neu-Wulmstorf
Floor area
9,703 sqm
Length/width/height
94 / 77 / 10.05
Type of building
Production facilities
Scope of supply and services
Turnkey
Period of construction
April 2020 – Feb. 2021
Description of the facility

BREMER has been contracted to build a production facility for Zajadacz GmbH in Neu-Wulmstorf.
The building is the extension to an existing hall by approximately 7,000 sqm for production and logistic space; separated by 2 fire walls.  A 2-storey mezzanine space is built above the 18 dock levellers on ground floor. A further storey can be added later.
The outer walls have an iso-façade and a cassette façade.
The floor is made from steel fiber concrete, the grounds are being paved.