next two logistics centre + money bin

in Hamburg

 
Building data
Location
Hamburg
Floor area
8,760 sqm
Length/width/height
Unit 1 (60 / 42 / 8.50 m) // Unit 2 (97 / 93 / 12.00 m)
Type of building
Logistics building
Scope of supply and services
Turnkey
Period of construction
May 2020 - March 2023
Description of the facility

BREMER has been contracted by builder-owner next two AG to build a turnkey logistics centre and money bin in Hamburg.
The construction is separated in two stages for units 1 and 2. Start of work for unit 1 is May 2020, with a duration of 11 month. Unit 2 is scheduled for March 2022 till March 2023.
Preliminary to construction, the demolition of the existing buildings takes place.
The quality of Hamburg grounds is often quite special as they have a high percentage of peat and clay. Therefore, the estate needs to be improved initially.
The building application for Unit 1 is particularly challenging. Special requirements need to be fulfilled to build a money bin. Employment protection for instance or structural measures: Natural daylight is not permitted in high security area.