Hall 40,000 m² + mezzanine 4,600 m²

384 / 108 / 13.95 m

Logistics building

Turnkey

Nov. 2021 - Oct. 2022

Description of the facility
BREMER was contracted to build the third construction phase of a logistics centre for Dietz AG in Hammersbach in the Limes intermunicipal industrial park.
It will be built as a direct extension to the second construction phase. The third construction phase consists of four additional units with a warehouse space of about 40,000 sqm. In addition, there is approx. 4,600 sqm of mezzanine space with partially developed office and social areas.